Continental demo site works completion
Works on the Continental demo site came finally to an end and the plant is ready for start-up and commissioning.
Site visits
La planta demostrativa de Talavera ha recibido varias visitas. A pesar de no haber entrado aún en funcionamiento, el concepto INTEXT está atrayendo la atención de diversos sectores del agua que han querido conocer las instalaciones. En esta imagen, la alcaldesa de...
Continental demo site electric works and programming
Electric and pneumatic connections have been finished and electric panels have been installed. Works on the Scada system to control Intext continental demo plant have started to develop the automation of the systems.
Continental demo site mechanical works completion
All pumps, water piping, flowmeters, level sensors, blowers, automatic and manual valves, water tanks and other auxiliary devices were installed at Talavera site.
SmallWat21 Congress
On June 17th and 18th of 2021, LIFE INTEXT project was presented in the 4th SmallWat21 Congress which took place virtually.
Second monitor´s annual visit
Today, LIFE INTEXT consortium received the second annual visit of our Neemo monitor to catch up on the project progress.
Mechanical instalation
Mechanical installation update: mechanical works for piping, pumps and accessories are ongoing.
Working on the wetlands and raceway
After civil works, wetlands and raceway waterprofing and different equipment have been installed.
Civil works end
After an unusual rainy winter, which has caused considerable delays, civil works have been concluded.
Third project meeting
The third project meeting has been virtually held. Project progress was updated and ongoing works were coordinated.